Construction to Commence

The demolition process will commence on 12 December 2022 and will be undertaken by Brajkovich Demolition with demolition works completed by the end of January 2023.

There will be no work undertaken from 24 December through to 2 January 2023.

Queries & Concerns

The project team will be making every effort to mitigate the impacts of construction throughout the duration of the project. Please see the Frequently Asked Questions below, which outline these measures in more detail.

However, if you do have any queries or concerns about the construction process, please complete the Enquiry Form or contact Andrew Watt on 08 9284 0910 or via email andrew@creatingcommunities.com.au

Frequently Asked Questions: Construction

Site Works

The demolition process will commence on 12 December 2022 and will be undertaken by Brajkovich Demolition with demolition works completed by the end of January 2023.

There will be no work undertaken from 24 December through to 2 January 2023.

No. The current structures will be demolished prior to Christmas 2022. The Melvista Aged Care Home will be a brand new, state oftheart home. 

Yes, the dilapidation condition required of the planning approval has now been cleared by both the SDAU and the City of Nedlands. The dilapidation process is an independently conducted professional survey the pre-existing state of nearby structures and accurately identifies any pre-existing building defects. All neighbours who agreed to a have a dilapidation survey conducted were provided with copies of the report for their property.  

It was not compulsory for neighbours to accept this offer of this independent inspection and report, as it is at the discretion of the neighbour however a dilapidation report was recommended to support the neighbour’s position in the event of any damage claim. 

Yes. Machinery such as excavators, piling rigs, trucks, bobcats and cranes will be used on the site. All endeavours will be made to limit impact from these machines. All construction activities will be conducted in accordance with the construction management Plan, which includes a site safety management plan. The site will be subject to the builder’s own safety auditing, and random safety inspections by the statutory authorities.

Trees and vegetation provide amenity and can help to activate spaces. As such, maintaining existing trees and vegetation within the site will be done where possible and in accordance with applicable approvals. The landscape plan for the site outlines a net additional 20+ trees which are incorporated as part of the project. Planteg garden beds will also be utilised throughout the site. Some 10 on site trees will need to be removed to accommodate the home with 4 trees retained. One tree located on the verge of Betty Street will need to be removed at the requirement of the authorities to accommodate fire services, with a total of 3 verge trees replaced. 

Oryx has already engaged a consultant arborist who has undertaken a detailed assessment and mandated tree protection zones. This consultant has an ongoing role to oversee the protection and health of both the verge trees and on-site trees to be retained.  

Parking and Traffic Management

As part of the construction Management Plan required to be reviewed and approved by the City of Nedlands, there will be a comprehensive traffic management plan in place. Most vehicle movement will occur through the site and the traffic management plan will outline the controlled movement of construction traffic. In collaboration with the City, the builder will proactively manage subcontractor parking implementing several strategies to manage construction trades parking. There will be dedicated spaces for subcontractor parking allocated within the City of Nedlands, but will not be adjacent to the Melvista site. The City of Nedlands will closely monitor parking in the area throughout the process. Once the site is further developed, the basement carpark will provide additional onsite parking. Transperth bus services in the area will not be impacted and will run as per usual.

Mitigating Impacts

Any demolition and construction work creates some noise. However, the noise from the construction of the building will be proactively mitigated due to the considered manner in which it will be constructed. Subcontractors will be mandated with clear instructions to minimise noise from the site, including controls over music. 

There will be some isolated times of greater noise, however every effort will be taken to keep excessive periods of construction noise to a minimum. Community communications will try to provide advance advice on periods when noise is to be expected. 

Work on the site will only take place during the hours that are permitted as per the City of Nedlands Building Permit regulations. 

During the demolition works the contractor will utilise sprinklers to control dust.   

Oryx has arranged for subcontractors to install security fencing and fabric screening to the street boundaries, and to spray paper hydromulch over the cleared lot to reduce dust impacts over the summer period.  

As part of the site works, excavation will need to take place which will result in the movement of soil.  The builder will be required to proactively manage dust suppression with the use of water trucks, sprinklers and site screening. Additionally, the builder will be required to maintain an orderly site throughout. 

Although there will be some exposure to the construction site from the surrounding streets, typically the site will be fenced screened until nearing completion. This will minimise exposure to the surrounding areas during construction.  

The site will have site security comprising fencing, security lighting and monitored CCTV. 

Project Updates

Once construction commences project updates will be provided on a semi-regular basis.

Click the button below to register for email updates.

Further Information
and Contacts

For more information or to raise any concerns about the construction process, please contact Andrew Watt:

Enquiry form